North Wing Phase 1 is complete, having 72 of 144 single-bed wards occupied along with M&E Infrastructure and services. Work is well underway for Phase 2 with superstructure due for completion in September 2019 to allow services to commence installation and be complete by February 2020.

Project value
£28M
Timeline
12 months
Client
Western Health and Social Care Trust + Farrans
Project information

Works on Altnagelvin Hospital also included the extension and refurbishment of the existing Chemotherapy Suite, the refurbishment of the ground floor of the Tower Block, and the construction of an underground car park.

 

Dowds completed a successful supply and installation of engineering services for the North Wing Extension of Altnagelvin Hospital. The ward block accommodation comprises 6 new departments with a total of 144 adult single-bedrooms, isolation wards, a renal dialysis suite, basement plantrooms and service tunnels.

Key challenges

We pushed for early engagement with our critical supply chain partners who understand the healthcare environment. We worked closely with them using their expertise alongside our own to ensure early agreement of detailed programme and final coordination of M&E services within very confined distribution routes.

David Algie, Associate Director (ARUP)

Dowds workmanship is without doubt the best I have seen and even a week from handover any remaining snags were either already actioned if not well underway. The coordination on the Altnagelvin was top drawer - no doubt we wouldn’t have got there without the professionalism, hard work and effort of Dowds Group.

We are always keen to hear from you. If you think we're the right fit for your project, get in touch.